Thu. Dec 26th, 2024

Construction activity for roadway improvements on Raitt Street between First Street and Fifth Street will begin on Monday, April 20, 2020 and will be ongoing through June 2020. The roadway improvements include new asphalt pavement with new curbs, sidewalks, curb ramps, and driveway aprons.

All residents and businesses will have access during the construction. Lanes in each direction will be maintained allowing through traffic. Construction hours will be from 8 a.m. to 5 p.m.

Should you have issues or questions, please contact the City of Santa Ana Inspector, Terry Moore at (714) 615-0886 or Senior Civil Engineer, Michael Ortiz at (714) 615-0892. We apologize for any inconveniences and thank you for understanding.

author avatar
Art Pedroza Editor
Our Editor, Art Pedroza, worked at the O.C. Register and the OC Weekly and studied journalism at CSUF and UCI. He has lived in Santa Ana for over 30 years and has served on several city and county commissions. When he is not writing or editing Pedroza specializes in risk control and occupational safety. He also teaches part time at Cerritos College and CSUF. Pedroza has an MBA from Keller University.

By Art Pedroza

Our Editor, Art Pedroza, worked at the O.C. Register and the OC Weekly and studied journalism at CSUF and UCI. He has lived in Santa Ana for over 30 years and has served on several city and county commissions. When he is not writing or editing Pedroza specializes in risk control and occupational safety. He also teaches part time at Cerritos College and CSUF. Pedroza has an MBA from Keller University.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.