Part of the I-5 will close for two nights for the I-5/Main Street Carpool Bridge Demolition. It is scheduled for Friday night, August 2, and Saturday, August 3, 2019.
There will be a full closure on northbound I-5 between SR-55 and SR-22, a full closure on Main Street between Santa Clara Avenue and Main Place Drive, partial closure on southbound I-5 between Gene Autry Way to Main Street, as well as various on and off ramp closures. Please see schedule below for time details and click here to see the interactive map.
Friday night, August 2, 2019:
- Main Street: Full closure, Santa Clara Avenue to MainPlace Drive (10 p.m. to 10 a.m.)
- NB I-5: Full closure, SR-55 to SR-22 (11 p.m. to 7 a.m.)
- NB SR-55 connector to NB I-5: Full closure (11 p.m. to 7 a.m.)
- NB SR-55 carpool connector to NB I-5: Full closure (10 p.m. to 8 a.m.)
- NB SR-57 carpool connector to NB I-5: Full closure (Midnight to 8 a.m.)
Saturday night, August 3, 2019:
- NB I-5: Full closure, SR-55 to SR-22 (11 p.m. to 9 a.m.)
- NB SR-55 connector to NB I-5: Full closure (11 p.m. to 9 a.m.)
- NB SR-55 carpool connector to NB I-5: Full closure (10 p.m. to 10 a.m.)
- NB SR-57 carpool connector to NB I-5: Full closure (Midnight to 10 a.m.)