Construction activity for roadway improvements on Raitt Street between First Street and Fifth Street will begin on Monday, April 20, 2020 and will be ongoing through June 2020. The roadway improvements include new asphalt pavement with new curbs, sidewalks, curb ramps, and driveway aprons.

All residents and businesses will have access during the construction. Lanes in each direction will be maintained allowing through traffic. Construction hours will be from 8 a.m. to 5 p.m.

Should you have issues or questions, please contact the City of Santa Ana Inspector, Terry Moore at (714) 615-0886 or Senior Civil Engineer, Michael Ortiz at (714) 615-0892. We apologize for any inconveniences and thank you for understanding.